Modern Council: Project Progress

Key

All project milestones met All project milestones met.
Project underway - no milestones due Project underway but no milestones due.
Majority of project milestones met Majority of project milestones met.
project off track milestones not met Project off track milestones have not been met.

 

 

Ref Description Project completion year Project Progress for 07/08 Project status
1 Be the ‘Employer of Choice’ in Thanet by:      
1a) improving the working environment for staff Year 2, 2009 Phase I completed, the contact centre is now located on the third floor in the old committee rooms. Work on the ground floor is underway, the Benefits service will be moving there end of June. “Moving Matters” microsite launched on the intranet. All project milestones met
1b) renewing the staff package – improve image recruitment and retention  Year 3, 2010 Proposals for the new staff discount  scheme, in partnership with KCC, will be presented at the staff conference, to be implemented June/July 08. All project milestones met
1c) reinvigorating the Council’s values – Service, Teamwork, Economics, and Pride Year 3, 2010 Managers’ Charter has been published.  Staff Charter in draft - will be subject to consultation. All project milestones met
2 Extend customer contact facilities across Thanet  
2a) open the integrated library/one-stop-shop in central Margate Year 2, 2009 Thanet's Gateway Plus opened on January 7th 2008, on budget. All project milestones met
2b) extend Council services to Ramsgate (using new library to provide Council services Year 4, 2011 Discussions with Kent Libraries will take place when plans for the re-build of Ramsgate Library are in place. Majority of project milestones met
2c) introduce a ‘Mobile Gateway’ with Kent County Council Year 1, 2008 Completed - this was launched at the Kent County show and was also show-cased at TDC during Customer Services Week, and also took part in the Gateway launch, visiting Ramsgate, Broadstairs and Westwood Cross. All project milestones met
3 Develop and publish a ‘People’s Charter’ that describes service standards to be delivered by the Council Year 1, 2008 Final draft sent to Cabinet.  It is now being distributed in July.  Now called "Residents' Charter" following feed-back from focus group All project milestones met
4 Develop Improvement Plan in response to Audit Commission recommendations Year 1, 2008 Advised by Audit Commission not to write an Improvement Plan.  Project withdrawn.  
5 Reduce the overall amount of accommodation used by the Council by:  
5a) reducing the storage of paper by 50%  Year 3, 2010 Good progress is being made in rolling out Corporate DIPS. Complaints and Ombudsman processes are live and 2 out of 3 housing modules. Work is underway with Housing, Development Control. All project milestones met
5b) relocating 70% of office staff into main building Year 4, 2011 Phase I complete – contact centre has been relocated to the third floor. All project milestones met
6 Increase customer satisfaction with the Council from 53% to 60% by 2011  
7 Achieve 3% cash savings year-on-year Year 4, 2011 Budget development for 2008-2011 will be progressed so as to deliver 3% cashable savings.  These proposals were reported to Cabinet and Council in February.
In respect of 2004-2007, the final AES will be due in July 2008 which requires annual savings of 3% (cashable and non cashable) which, based on the forward look for 07/08, will be achieved.
All project milestones met
8 Enhance two-tier working in Kent and within East Kent – for example waste, housing and parking services Year 4, 2011 Joint Services Committee and joint arrangements Scrutiny Committee proposals agreed by Council on 8 May 08. Programme being established by East Kent Chief Executives to run ahead of first Joint Services Committee All project milestones met
9 Develop comprehensive information management system to support delivery of Corporate Plan to include:   
9a) Develop a consistent framework of plans and strategies to underpin the delivery of the Corporate Plan Year 1, 2008 Audit of existing plans and strategies carried out and results presented to CMT.  Report going to Cabinet in August All project milestones met
9b) Develop project management arrangements within the six themes Year 1, 2008 Briefing sessions completed for all project managers. Project Briefs completed for all projects across the themes All project milestones met
9c) Set up document management/retrieval and storage system Year 2, 2009 Individual Sharepoint sites set up for each of the six Corporate Plan themes. 
Meeting held to agree scope of project to develop Sharepoint site providing document repository and development of database to provide search capability.
Meetings underway with each Head of Service to identify all documents to be included, and to highlight those that may still need to be produced.
Meetings held to define the functionality and visual identity of the database that will drive the site and the site itself.  Draft guidance for new Publication Scheme reviewed – awaiting final information in March.
Draft database written and internet presentation style agreed.
All project milestones met
10 Implement a complaints logging and response system including Freedom of Information and Member enquiries  Year 2, 2009 The Council's new complaints system went live on 1st August 2007 and is being monitored by the Complaints Working Group.  A separate process for managing Ombudsman’s complaints is in place. Root cause analysis work is also being carried out which will enable service improvement and, ultimately, reduce the amount of complaints being received. Continuous improvement to the process are being made, in response to end user feedback, moving from 75% to 81% in January. Work underway to review ways to reduce end user dependence on Project Office for support with processing. All project milestones met

 

Next: Modern Council: Targets for future years

 