Construction timeline

The scheme is due to start in November 2011 and will run until December 2012.

 

Phases of construction work

  • Stone Pier (Harbour Arm): November 2011 until March 2012
  • Slipway Area: April 2012 until August 2012
  • North Wall: April 2012 until August 2012
  • Revetment (steps): November 2011 until December 2012
  • South Wall: January 2012 until May 2012

Margate flood protection phases of construction

 