Local Plan timetable

The council has agreed a timetable for preparing a new Local Plan. This timetable is set out on this page. It now comes into effect.

This Plan will be produced under a new plan-making system. This system has some different stages compared to the previous one. It also includes a series of gateways. These must be completed before a public examination takes place.

We expect the first public consultation to take place at the end of August this year. This is known as the Scoping Consultation. During this time, the council will be seeking views on several matters. This includes what the plan should contain. It also includes how future engagement on the plan should be carried out. Further details will be provided at that time.

Stage

Proposed date(s)

Local Plan Timetable (Reg 8)
Notice of Intention to Prepare a Local Plan (Reg 19)
12 June 2026
Scoping Consultation (Reg 20) 24 August – 9 October 2026
Gateway 1 (Reg 21) 30 October 2026
Consultation on proposed local plan content and evidence (Reg 23) 28 January 2027 – 12 March 2027
Gateway 2 (Reg 26) 23 July 2027
Consultation on the proposed local plan (Reg 27) 28 October 2027 – 24 December 2027
Gateway 3 (Reg 31) 21 January 2028
Submission (Reg 34) 10 March 2028
Examination (Reg 35) April 2028 – January 2029
Adoption (Reg 39) February 2029

Help & support

Did you find this page useful?

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Please select a reason(Required)
Please select a reason*
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.