Update on the improvement works to Berth 4 / 5 at the Port of Ramsgate
The aggregate berth (Berth 4 / 5) at the Port of Ramsgate was decommissioned and removed in November 2020 as it had reached the end of its operational life. Construction work on the new berth started earlier this year, following the completion of an Environmental Impact Assessment (EIA) and the granting of both planning permission and a Marine Licence.
Construction work has progressed well since it started in June. Major parts of the work such as the dredging, piling and installation of the new berth itself are now complete. One of the two gangway bridge sections has also now been installed which will link the floating berth back to land.
The project had originally been programmed for completion at the end of August but some land-based parts of the project and ancillary work on the floating berth will now continue into September.
A variation to the marine licence required for the construction of the berth has been granted allowing the work on site to continue until the end of September. There will be no adverse impact on the environment as a result of this extension.
When complete, the berth will enable the safe berthing of aggregates vessels and the transfer of aggregates from ship to shore.
Newsroom
See allLike many local councils, 2024 marks a significant milestone for Thanet District Council as it is 50 years since it was inaugurated.
Thanet District Council is inviting members of the public to learn more about its designs for the Green Campus, one of Ramsgate’s Levelling Up Fund regeneration projects. The Green Campus will create spaces for training, enterprise and light industry along Military Road. It will be a self-sufficient destination for enterprise and skills development.
A Thanet resident has been successfully prosecuted for fly-tipping the same item in two different areas of the district.