Berth replacement update
The project to replace berth 4/5 at the Port of Ramsgate is to be delayed until early 2021. This is because the council as the planning authority has determined that an Environmental Impact Assessment (EIA) is needed in relation to the replacement of the berth.
The proposed work constitutes permitted development as described in Schedule 2, Part 18 Class A of the The Town and Country Planning (General Permitted Development) (England) Order 2015. As such a prior planning approval application for the project was submitted to the council as the Local Planning Authority in August.
As the council is the applicant the decision on the prior approval application must be made by members of the planning committee rather than officers.
A contract has been awarded to the contractor BAM Nuttall Ltd for the replacement works and will involve the reuse of one of the pontoons that are currently moored in the Royal Harbour at Ramsgate.
The council has a contractual obligation to replace berth 4/5 which is at the end of its operational life.
Newsroom
See all
Thanet District Council’s planning committee has approved plans for the reopening of the Theatre Royal Margate. This decision marks a major milestone for the second oldest theatre in the United Kingdom, which has been closed since April 2022. The approved plans will breathe new life into the Grade II* listed building. The project will focus […]
Thanet District Council is inviting people to a free day of family fun, wellbeing and safety this summer. The Community Day will happen at the Memorial Recreation Ground in Broadstairs on Wednesday 29 July 2026. Open to the public from 11am to 3pm, the event brings together two popular community initiatives: the Thanet Games and […]
In a statement to Parliament earlier today (Thursday 16 July 2026), the Secretary of State has announced that Kent and Medway will be served by four unitary councils from 1 April 2028.